Problem
About a third of every sprint commitment missed, and nobody could see why until someone burned out.
At Vettx I managed delivery for a development team of about fifteen that cost the company around $80K a month, and it finished roughly 65% of what it promised each sprint. Workload was invisible, estimates were guesses, and half the management lived in spreadsheets. None of that was anyone's job to fix. I made it mine.
About a third of every sprint commitment missed, and nobody could see why until someone burned out.
One hub with six modules and one login: live workload, refinements, retros, DevOps requests, holidays and admin.
Delivery went from ~65% to ~100% of commitments, and 15 people ran their ceremonies in it.
How do you get a team to adopt a tool when nobody has the budget to approve it?
Jira had all the data, but nobody opens twelve filters before a daily. Developers didn't push back on overload because they couldn't see it either. It wasn't a design ticket, a product ticket or an engineering ticket, so it just sat there.
The first module was Sprint Analytics: active sprint, history, planning and initiatives, with the load of each person on one screen.
Pitching an internal tool to a company that was cutting costs was going nowhere. I built analytics in the evenings with my own tools and brought it to a daily.
Nobody had to approve a tool that already answered the question in the same meeting where people asked it.
Claude reads each ticket blind, without points or votes, and rates its complexity against a frozen rubric. A small statistical model turns that rating into points. Below a confidence threshold, the ticket goes back to the humans.
I backtested it the boring way: calibrated on sprints 70 to 79, tested from 80 on. It plateaued around 80%, and people still agreed with each other more than with the model. So it became the opening estimate. That was the right job for it.
Refinements with live voting and async check-ins, retros with lead evaluations, one DevOps request and approval chain, synced holiday calendars and per-capability permissions with a view-as mode.
It replaced a paid scrum poker tool and half a dozen manual chores. The PO started getting refinement prep before the meeting, not during it.
Over the following sprints the team went from finishing around 65% of its commitments to landing at or above 100% almost every time. Workload got balanced before the sprint, instead of discovered when it failed.
The most valuable problems are the ones with no owner. Nobody will hand them to you.
Internal tools don't need a mandate. They need to answer a question people already have, in the room where they ask it.
Vettx retired the hub in November 2026. It still runs as an archive on the last production snapshot.